Rooftop Solar Basics for Bangladesh
Everything a homeowner or factory owner needs before talking to an installer: how rooftop solar works on Bangladesh's grid, how big a system you need, what it costs and how long it takes to pay back.
Updated
Read in this order
Four short guides that take you from “how does it work?” to a system size and a payback estimate you can check against installer quotes.
- 1How rooftop solar worksPanels, inverters and the grid — and what happens during load-shedding and the monsoon.7 min read
- 2Sizing your systemThree numbers decide your system size: electricity use, roof space and sanctioned load.6 min read
- 3Cost and paybackWhat you pay for, how to read a quote, and a calculator to estimate payback.8 min read
- 4Solar glossarykWp, sanctioned load, anti-islanding and every other term, in plain language.5 min read
Quick answers
The questions homeowners and factory owners ask us most. Terms you don't know are in the glossary.
Does rooftop solar work during load-shedding?
A standard grid-tied system switches off when the grid goes down. This is a safety feature called anti-islanding, which protects line workers. If you need power during outages, ask an installer about a hybrid system with batteries.
Grid-tied, hybrid or off-grid? →Do solar panels work during the monsoon?
Yes, but output drops on cloudy days. Panels still produce power from diffuse light, and the yearly generation figures installers quote should already include the lower monsoon months.
Sun, monsoon and haze →How much roof space do I need?
As a rule of thumb, allow about 100 square feet of shade-free roof for every kWp of panels. Water tanks, stair rooms and neighbouring buildings that cast shade reduce the usable area.
Measure your roof →How big a system am I allowed to install?
Under the 2025 net-metering guideline, a system can be up to 100% of your sanctioned load. Both single-phase and three-phase connections are eligible.
Check your sanctioned load →Can I sell electricity back to the grid?
Yes. Under net metering, units you export are recorded by a bi-directional meter and credited against the units you import. Credit left at the end of each three-month settlement period is paid at your utility's bulk rate into your bank or mobile banking account.
Read the net-metering guide →How long do solar panels last?
Good-quality panels are commonly sold with a 25-year performance warranty and can keep working beyond it at slightly reduced output. Inverters have a shorter life and usually need replacing at least once during the life of the panels.
Do solar panels need cleaning?
Yes. Dust, bird droppings and soot lower output, especially in the dry season. Rinse panels with clean water and a soft brush — never abrasive cleaners — and do it early in the morning or late in the day when the glass is cool.
Is financing available for rooftop solar?
IDCOL, a government-owned financial institution, finances renewable energy projects in Bangladesh, including rooftop solar. Some banks also offer green financing. Terms and eligibility vary by programme.
IDCOL financing programmes →