The short version
Net metering lets you connect a rooftop solar system to the grid and get credit for the electricity you don't use. Your home or factory uses its solar power first. When the panels make more than you need, the surplus flows to the grid through a bi-directional meter, and those units are set against the units you take from the grid at night or on cloudy days. You pay only for the difference.
Bangladesh's rules are set by the Net Metering Guideline 2025, issued by the Power Division with SREDA. It applies to every distribution utility — BPDB, DPDC, DESCO, BREB and its Palli Bidyut Samitis, WZPDCL and NESCO — and you apply through your own utility.
What changed in 2025
The 2025 guideline replaces the 2018 guideline, its 2019 amendment and the circulars issued since, and opens net metering to far more consumers:
- Bigger systems. Up to 100% of your sanctioned load, up from 70%.
- Every consumer in one rulebook. Single- and three-phase consumers, and prepaid and smart meters, are covered by the guideline itself.
- Online applications. Apply and track every stage on the Power Division's portal.
- Quarterly payouts. Leftover credit is paid every three months, into a bank or mobile banking account or by cheque.
Who can apply
You can apply for net metering if:
- You are a legitimate consumer of the distribution utility in your area. New connections can apply for net metering at the same time.
- You have no unpaid electricity bills when you apply.
- Your system generates only from renewable sources, such as solar. Power from a generator cannot be net-metered.
- You own the premises, or have valid permission from the owner or their representative.
- The system sits on a roof, parking shed, garage, factory shed, boundary wall or open space you control, at a location with a utility meter.
- You use the electricity yourself first and export only the surplus.
Rooftop systems installed before the guideline can apply to convert to net metering. If you can prove when the system was installed, the panel standards may be relaxed for it.
Consumer categories covered
Every tariff category below can apply, as long as it meets the conditions above. You'll find your category and connection voltage on your electricity bill.
| Connection | Eligible categories |
|---|---|
| Low voltage (LT), 230/400 V | Residential (LT-A), irrigation pumps (LT-B), industry (LT-C1), education, religious and charitable institutions and hospitals (LT-D1), street lights and water pumps (LT-D2), battery charging stations (LT-D3), commercial and office (LT-E) |
| Medium voltage (MT), 11 kV | Residential (MT-1), commercial and office (MT-2), industry (MT-3), general (MT-5), battery charging stations (MT-7), irrigation pumps (MT-8) |
| High voltage (HT), 33 kV | General (HT-1), commercial and office (HT-2), industry (HT-3) |
| Extra-high voltage (EHT), 132/230 kV | All consumer categories |
How big a system you can connect
The guideline sets two limits:
- Your sanctioned load. The inverter's AC output cannot be more than your sanctioned load — 100% of it, up from 70% under the old rules. Single-phase and three-phase consumers are treated the same way.
- Your transformer. Medium-, high- and extra-high-voltage consumers are also limited to 80% of the rated capacity of their transformer, or of their parallel transformers combined.
The limit is on the inverter's AC output, in kW, not on panel capacity in kWp. The application asks for both. What matters is that your AC output stays within the approved capacity: a solar accounting meter records your highest output each month. If it goes over, the utility sends a warning letter. If it happens again, the utility can move to cancel the agreement, and a consumer who goes over is not paid for leftover credit at settlement.
Want a larger system? Apply separately to your utility. If the utility agrees, it sends the request to a grid-stability committee, and the Power Division decides. Our sizing guide shows how to check the limit against your roof and electricity use.
How exported units are credited
Your utility still bills you every month. Each bill counts the units you imported from the grid, the units you exported and any credit brought forward from the month before.
Three rules decide how much credit you get:
- A 10% maintenance charge. In a month when you export more than you import, the utility keeps 10% of the net exported units as a distribution-system maintenance charge. The other 90% are added to your credit.
- Off-peak first. If your meter records peak and off-peak hours separately, exported units are set against your off-peak units first, then against peak units.
- Fixed charges still apply. Even in a month with no energy charge, you pay the demand charge, meter rent, VAT and any other fixed charges.
Each month, the utility tells you your imports, exports, net exports, credit and settlement units by SMS, email, app or web portal. The meter display shows the totals too.
Quarterly settlement and payouts
Credit carries forward from month to month, but not forever. The guideline uses a three-month settlement period that ends with your March, June, September and December bills. At the end of each one:
- Any credit left over becomes “settlement units”.
- The utility pays for them at the bulk rate set by BERC. For consumers connected at 33 kV or below, that is the utility's bulk tariff at 33 kV.
- The money goes to the account you chose when you applied — a bank account (by BEFTN or NPSB), a mobile banking account (Nagad, bKash or Rocket), or a cheque you collect. The account must be in the consumer's name.
- Your credit resets to zero for the next period.
The Tk 10.50 export incentive
A Power Division notification of 1 September 2026 pays Tk 10.50 for each unit exported to the grid from rooftop systems installed under this guideline by 28 February 2027. The rate lasts until 28 February 2030 and is paid into your bank account every three months — never in cash. That is well above the bulk rate, and makes exporting worth more while it lasts.
The notification introduces the package as an incentive for rooftop solar with batteries, but doesn't repeat that condition when it sets the rate, or say how the rate combines with the 10% maintenance charge. Ask your utility, in writing, whether your system qualifies. The government policies page has the details.
On a prepaid or smart meter, your credit units are used first. Nothing is deducted from your recharge balance while you still have credit.
Three worked bills
These examples come from the guideline itself (Appendix 5). The tariffs are the ones it uses and will not match today's rates — check your own bill for current figures.
A home that still imports
A residential consumer of a Palli Bidyut Samiti has a 10 kW sanctioned load and a 10 kW system. In April they import 500 units and export 350, with no credit from March, so they are billed for 150 units.
| Without solar | With net metering | |
|---|---|---|
| Units billed | 500 | 150 |
| Highest slab reached | 5th (401–600 units, ৳12.67) | 2nd (76–200 units, ৳7.20) |
| Energy charge | ৳4,123 | ৳935 |
| Demand charge (10 kW × ৳42) | ৳420 | ৳420 |
| VAT (5%) | ৳227 | ৳67.75 |
| Total, before meter rent | ৳4,770 | ৳1,422.75 |
The bill falls by ৳3,347 — about 70% — because solar removes the most expensive slabs first.
An office that exports more than it uses
A commercial consumer of DESCO with a 20 kW sanctioned load and a 20 kW system imports 1,500 units in November (500 off-peak, 1,000 peak) and exports 2,000. They bring forward 200 units of credit from October.
- Net exports: 2,000 − 1,500 = 500 units.
- After the 10% maintenance charge: 90% × 500 = 450 units of new credit.
- Credit carried into December: 450 + 200 = 650 units.
- Bill: no energy charge, only the demand charge of ৳1,800 plus 5% VAT — ৳1,890.
A factory paid at the end of a settlement period
An industrial consumer of DPDC with a 50 kW sanctioned load and a 50 kW system imports 4,500 units in June and exports 4,000. They bring forward 2,000 units of credit from May. The credit covers the 500 units they imported beyond their exports, leaving 1,500 units at the end of the settlement period.
| Settlement units | 2,000 − (4,500 − 4,000) = 1,500 units |
|---|---|
| Value at DPDC's bulk rate | 1,500 × ৳8.56 = ৳12,840 |
| Less demand charge and VAT | ৳2,400 + ৳522 |
| Paid to the consumer | ৳9,918 |
Meters and equipment
A net-metered system needs up to three meters:
- Net meter (required). A single- or three-phase bi-directional smart meter at the point where you connect to the grid, recording imports and exports separately. If your existing meter can be reprogrammed to do this, it doesn't need replacing.
- Solar accounting meter (required). Records what your system generates, including its highest monthly output, under both the CAPEX and OPEX models.
- Self-consumption meter (optional). Measures how much electricity your premises use in total.
The utility usually buys, tests, installs, maintains and reads the net meter. You pay for it, along with any changes needed to the utility's network or your meter board. You can buy the meter yourself if the utility or SREDA approves the brand and model. Some utilities may offer the net meter and a grid-tied inverter in monthly instalments, so ask yours. The installed system must also allow remote online monitoring.
Panels, inverters, charge controllers and net meters must meet the Bangladesh (BDS) or equivalent IEC standards. SREDA approves equipment model by model and lists approved models on its website, so ask your installer to confirm the models in your quote are on the list.
How to apply, step by step
Apply on the Power Division's net-metering portal (opens in a new tab) (nem.powerdivision.gov.bd), or on paper to the head of your local utility office, quoting your consumer number. Most installers prepare and submit the application for you.
- 1
Apply online
You or your installer
Submit the application on the Power Division's portal, or on paper at your utility office. You get an SMS and email confirmation and can track each stage online.
- 2
Site inspection
Your utility
The utility checks your premises, the connection point and whether its own network needs changes — any such cost is yours.
- 3
Approval
Your utility · Within 10 working days of applying
The utility issues permission to install. For online applications, the approval email is the permission letter.
- 4
Install the system
You and your installer · Within 8 months of approval
Install using SREDA-approved equipment, complete the system checklist, upload it and ask the utility to evaluate the system.
- 5
Evaluation
Your utility
The utility inspects the installed system against the approved design and the technical standards.
- 6
Agreement and connection
You and your utility · Within 15 working days of your evaluation request
You sign the net-metering agreement. The signing date is your commercial operation date, when credits start.
What the application asks for
- Your consumer category, and whether you are using the CAPEX or OPEX model
- Your NID or passport number — or, for a company, its registration and trade licence numbers — and contact details
- The site address, GPS coordinates and whether the property is owned outright, mortgaged or leased
- Your utility, consumer account number, tariff category, sanctioned load and current meter number
- The proposed system's AC capacity (kW), DC capacity (kWp) and the ratio between them
- The connection voltage, and details of any batteries you plan to use
- For commercial and industrial consumers: daytime peak and minimum demand, on working days and holidays
- The bank, mobile banking or cheque details for settlement payouts
For help before you apply, contact SREDA's National Solar Help Desk (opens in a new tab), which covers site assessment, the application process, technical standards and financing.
Paying upfront or not: CAPEX and OPEX
The guideline recognises two ways to put solar on your roof:
- CAPEX — you pay for the system, own it and keep all the savings and payouts. This is the usual model for homes, and our cost and payback guide covers it.
- OPEX — an investor company installs, runs and maintains the system at its own cost. You buy the electricity it produces at a rate set in your contract, usually below your utility's tariff.
Under OPEX, you sign the contract with the investor before you apply to the utility, and the net-metering agreement is signed by all three parties. The contract should set the tariff for each year, the payment method, how monthly meter readings are recorded, any security deposit and what happens to the system when the contract ends or is cancelled early. If you don't pay the investor for two months in a row, the utility can act on their complaint, up to disconnecting your supply.
For financing a system you own, see IDCOL financing programmes.
New connections and load increases
A Power Division circular of 23 December 2025 makes net-metered rooftop solar a condition of new connections for buildings with at least 1,000 square feet of roof usable for 20 years. The minimum size depends on your category — for example, at least 3 kW for a three-phase home with a load of 10 kW or more, and at least 20% of the approved load for industrial and commercial consumers of 10 kW or more. Existing consumers who apply for more load must install solar on the extra load at the same rates.
The full table is on our government policies page. Ask your utility how the rule applies to you before you apply for a connection or more load.
Common questions
Who can apply for net metering in Bangladesh?
Any single-phase or three-phase consumer of a distribution utility who has no unpaid electricity bills, generates only from renewable sources such as solar, and owns the premises or has the owner's permission. Residential, commercial, industrial, institutional and irrigation consumers are all covered.
How big a solar system can I connect under net metering?
The inverter's AC output can be up to 100% of your sanctioned load. Medium-, high- and extra-high-voltage consumers are also limited to 80% of their transformer's rated capacity. Larger systems need a separate application, decided by the Power Division.
Will my utility pay me for the electricity I export?
Yes. Exported units first offset the units you import. Any credit left at the end of each three-month settlement period — March, June, September and December — is paid into your bank or mobile banking account, or by cheque.
What rate are exported units paid at?
Credit carried within a settlement period offsets imports at your normal tariff. Credit left at the end of the period is paid at the bulk rate set by BERC for your utility, which is usually lower than the retail rate on your bill. In both cases, 10% of each month's net exports is kept as a distribution maintenance charge. Separately, a September 2026 incentive pays Tk 10.50 per exported unit, until February 2030, for systems installed by 28 February 2027.
The Tk 10.50 export incentive →
How long does the net-metering application take?
The utility must approve or reject the application within 10 working days. You then have up to 8 months to install, and the utility must sign the agreement within 15 working days of your request for evaluation.
Who pays for the net meter?
You do. The utility normally buys, tests, installs and reads the bi-directional meter, but its cost — and the cost of any changes to the utility's network — is borne by the applicant. You may buy the meter yourself if the model is approved by your utility or SREDA.
Can I use net metering with a prepaid meter?
Yes. Under the 2025 guideline, prepaid and smart meters can be made bi-directional. Your credit units are used first, and nothing is deducted from your recharge balance while you still have credit.
Can I connect a rooftop system I already have?
Yes. Systems installed before the guideline can apply to convert to net metering, and the panel standards may be relaxed for older systems if you can prove when they were installed.
Can I get net metering without paying for the system upfront?
Yes, through the OPEX model: an investor company installs and runs the system at its own cost, and you buy the electricity it produces at an agreed rate, usually below your utility's tariff. You sign the OPEX contract before applying to the utility.
Does a net-metered system work during load-shedding?
Not on its own. A grid-tied inverter switches off when the grid goes down, so it cannot feed lines that workers expect to be dead. For backup, ask an installer about a hybrid system with batteries.
What happens during load-shedding →
Sources
- Net Metering Guideline 2025 (Bangla), Power Division (opens in a new tab)
- Net Energy Metering online portal, Power Division (opens in a new tab)
- National Solar Help Desk, SREDA (opens in a new tab)
- Circular on rooftop solar for new connections, Power Division (23 December 2025) (opens in a new tab)
- Notification on the rooftop solar incentive tariff, Power Division (1 September 2026) (opens in a new tab)
Rules and tariffs change. See how we check our information on our sources page.